Project Start Date: Mon 1/2/06
Project Finish Date: Thu 7/13/06
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | Microsoft Project 2003 Personal Trainer Book | 139 days | Mon 1/2/06 | Thu 7/13/06 | ||
| 2 | Write Microsoft Project 2003 courseware | 83 days | Mon 1/2/06 | Wed 4/26/06 | ||
| 3 | Research Microsoft Project 2003 courseware | 10 days | Mon 1/2/06 | Fri 1/13/06 | Melissa Peterson | |
| 4 | Create outline | 4 days | Mon 1/16/06 | Thu 1/19/06 | 3FS-2 days | Melissa Peterson |
| 5 | Write lessons | 3 mons | Fri 1/20/06 | Thu 4/13/06 | 4 | Melissa Peterson |
| 6 | Editorial meeting | 55.13 days | Wed 1/25/06 | Wed 4/12/06 | ||
| 7 | Editorial meeting 1 | 1 hr | Wed 1/25/06 | Wed 1/25/06 | ||
| 8 | Editorial meeting 2 | 1 hr | Wed 2/1/06 | Wed 2/1/06 | ||
| 9 | Editorial meeting 3 | 1 hr | Wed 2/8/06 | Wed 2/8/06 | ||
| 10 | Editorial meeting 4 | 1 hr | Wed 2/15/06 | Wed 2/15/06 | ||
| 11 | Editorial meeting 5 | 1 hr | Wed 2/22/06 | Wed 2/22/06 | ||
| 12 | Editorial meeting 6 | 1 hr | Wed 3/1/06 | Wed 3/1/06 | ||
| 13 | Editorial meeting 7 | 1 hr | Wed 3/8/06 | Wed 3/8/06 | ||
| 14 | Editorial meeting 8 | 1 hr | Wed 3/15/06 | Wed 3/15/06 | ||
| 15 | Editorial meeting 9 | 1 hr | Wed 3/22/06 | Wed 3/22/06 | ||
| 16 | Editorial meeting 10 | 1 hr | Wed 3/29/06 | Wed 3/29/06 | ||
| 17 | Editorial meeting 11 | 1 hr | Wed 4/5/06 | Wed 4/5/06 | ||
| 18 | Editorial meeting 12 | 1 hr | Wed 4/12/06 | Wed 4/12/06 | ||
| 19 | Functionality check | 6 days | Wed 4/19/06 | Wed 4/26/06 | 5 | Steve Meinz,Melissa Peterson[50%] |
| 20 | Edit and proof text | 5 days | Wed 4/19/06 | Tue 4/25/06 | 19SS | Kitty Rogers,Melissa Peterson[50%] |
| 21 | Send courseware and images to O'Reilly | 0 days | Wed 4/26/06 | Wed 4/26/06 | 20,19 | |
| 22 | Publish book | 56 days | Thu 4/27/06 | Thu 7/13/06 | ||
| 23 | Design | 6.5 days | Thu 4/27/06 | Fri 5/5/06 | ||
| 24 | Prepare art files | 4 days | Thu 4/27/06 | Tue 5/2/06 | 21 | Illustrators[200%] |
| 25 | Approve cover text and image | 1.5 days | Wed 5/3/06 | Thu 5/4/06 | 24 | Mark Brokering,Bill Takacs,Laurie Petrycki,Michele Filshie |
| 26 | Approve CD text and color | 1 day | Thu 5/4/06 | Fri 5/5/06 | 25 | Michele Filshie,Bill Takacs,Laurie Petrycki,Mark Brokering |
| 27 | Edit and proof text | 45 days | Thu 4/27/06 | Wed 6/28/06 | ||
| 28 | Edit manuscript | 2 wks | Thu 4/27/06 | Wed 5/10/06 | 21 | Michele Filshie |
| 29 | Upload text and images to server | 4 hrs | Thu 5/11/06 | Thu 5/11/06 | 28 | Michele Filshie |
| 30 | Convert text from Word to Frame | 1 wk | Thu 5/11/06 | Thu 5/18/06 | 29 | Andrew Romano,Tim O'Reilly,Nate Torkington |
| 31 | Check converted text | 1 day | Thu 5/18/06 | Fri 5/19/06 | 30 | Production editor |
| 32 | Quality Control 1 | 18.5 days | Fri 5/19/06 | Wed 6/14/06 | ||
| 33 | Proof text | 1 wk | Fri 5/19/06 | Fri 5/26/06 | 31 | Production editor |
| 34 | Write index | 1 wk | Fri 5/19/06 | Fri 5/26/06 | 33SS | Indexer |
| 35 | Enter proofing edits | 1.5 wks | Fri 5/26/06 | Tue 6/6/06 | 33,34 | Production editor |
| 36 | Check edits | 1 day | Wed 6/7/06 | Wed 6/7/06 | 35 | Production editor |
| 37 | Read over QC1 proof | 1 wk | Thu 6/8/06 | Wed 6/14/06 | 36 | Michele Filshie |
| 38 | Quality Control 2 | 9 days | Thu 6/15/06 | Tue 6/27/06 | ||
| 39 | Proof index | 1 day | Thu 6/15/06 | Thu 6/15/06 | 37 | Production editor |
| 40 | Prepare final index | 1 day | Fri 6/16/06 | Fri 6/16/06 | 39 | Indexer |
| 41 | Proof text | 3 days | Fri 6/16/06 | Tue 6/20/06 | 39 | Production editor |
| 42 | Enter proofing edits | 4 days | Wed 6/21/06 | Mon 6/26/06 | 41 | Production editor |
| 43 | Check edits | 1 day | Tue 6/27/06 | Tue 6/27/06 | 42 | Production editor |
| 44 | Final Quality Control | 1 day | Wed 6/28/06 | Wed 6/28/06 | ||
| 45 | Review final draft | 4 hrs | Wed 6/28/06 | Wed 6/28/06 | 43 | Production manager |
| 46 | Enter edits | 4 hrs | Wed 6/28/06 | Wed 6/28/06 | 45 | Production manager |
| 47 | Print Book | 18 days | Tue 6/20/06 | Thu 7/13/06 | ||
| 48 | Secure printer | 1 wk | Tue 6/20/06 | Mon 6/26/06 | Production manager | |
| 49 | Send cover files to printer | 0 days | Mon 6/26/06 | Mon 6/26/06 | 48,25 | Production manager |
| 50 | Send text files to printer | 0 days | Wed 6/28/06 | Wed 6/28/06 | 46,49FS+2 days | |
| 51 | Print book | 6 days | Thu 6/29/06 | Thu 7/6/06 | 50 | Printer |
| 52 | Ship to warehouse | 4 days | Fri 7/7/06 | Wed 7/12/06 | 51 | Printer |
| 53 | Review and sign off on vendor invoices | 1 day | Thu 7/13/06 | Thu 7/13/06 | 52 | Production manager |
| 54 | Complete book | 0 days | Thu 7/13/06 | Thu 7/13/06 | 53 |